Relocating a house onto your lot in Queensland
Moving a house to a new site is building work that isn’t “accepted” (self-assessable) work, so it’s likely to need a building approval from a building certifier. The council where the house will sit is a referral agency and decides on a security bond first.
The approval lapses if the work isn’t finished, with its final inspection, within 1 year. That period can be extended once, by up to 6 months, if you apply to the local government in writing before the year ends.
Before the house moves, the electricity network must confirm in writing that supply at the old site has been removed (the rule in South East Queensland), and the new site needs a new connection application. An oversize-load permit through the NHVR is needed, and a police wide-load escort needs that permit first. Houses built before 1990 may contain asbestos, which must be removed by a licensed removalist before transport, or an exemption obtained.
Contract and deposit
For a home (domestic) building contract of $20,000 or more, the deposit cap is generally 5%; over $3,300 and under $20,000, 10%; up to 20% only where more than half the contract price is for off-site work. Check a contractor’s licence on the QBCC licensee register.
What the kit covers
- Step order
- Who does what (council, certifier, engineer, plumber, electrician, removalist)
- Buyer protection
- Removalist contract checklist
- Local sections for all 6 councils (the house relocation kit's Ipswich section is partial)
- Published fees and timeframes
- Tracker and chase-up email examples
- The founder’s lessons learned
Councils
General information only, not advice. ClearDA kits and the screener give general information drawn from official sources. They are not legal, planning, building, engineering or financial advice, and they are not a council's or building certifier's decision. Rules change, and council requirements, planning scheme overlays (such as flood, bushfire or heritage overlays) and site conditions vary from property to property. Each kit shows the date its sources were last checked, and doesn't cover changes after that date. Before you act, always confirm with your local council, a building certifier or another QBCC-licensed or suitably qualified professional, and use a licensed tradesperson where the law requires one.